Friday, 15 August 2008

Day 82 - Goodbye Kitchen

The kitchen was next to the skip. It has served us well for the past couple of years but quite frankly it had to go. The cooker is now stationed at the front door prior to delivery to the tip and the cupboards were destroyed by yours truly.


Steve continued his endless plastering this time the cloakroom and parts of the kitchen were done. Richard was here with Paul finalising construction on the porch roof and getting it ready for roofer James on Tuesday of next week

James will be here on Monday to put the fascia on ready and Paul will be on site too. Richard is away next week as he has a holiday taking his Mum on a cruise....isn't he a nice boy to him Mum.

At the end of the weekend here is the state of play. Upstairs is pretty much complete except for facia plates on all the electrics and lighting fittings. Some more minor woodwork to do on the stairs and in the second bedroom. Downstairs the plastering still needs work on two rooms, the kitchen needs a minor skimming on a couple of walls. Again the electrics need work as do the plumbing for the extra radiators we have discussed with Phil. Making a guess I would say we have 2-3 weeks left. We are still awaiting kitchen quotes.

Our sad looking kitchen.