Wednesday, 8 October 2008
Day 109 - Boiler Working
Everything is now done apart from the snags, we have a friend who is in the trade coming round tomorrow night who said he would give us a hand......and have a beer with me of course :)
Tuesday, 7 October 2008
Day 108 - Boiler
Problem 1 - Two leaks in the internal pipework, the first a minor dripping in the study that needed a little solder on the join, the second a poor seal on a radiator valve.
Problem 2 - Open valve on the second bedroom radiator has meant we have water coming through the kitchen ceiling through a light fitting, thankfully its sealed for fireproofing so its still OK.
Problem 3 - Duff boiler, well this one was the show-stopper. The boiler is broken, Phil says its the second one out of two to have this problem but the engineer came over and says he will have the required part for tomorrow morning.
Not a good day, still no heating although the landing is looking good with its first coat on all the walls and ceiling.
Wednesday, 1 October 2008
Day 107 - Coving Complete
Richard is off now to finish work on his house, Paul has to lay us a new drive and Phil has to install our new oil tank to hook it up to the boiler.
We have now been left with the task of creating a snag list of things that aren't quite right or incomplete. We now await out bill and final pieces before we write up our closing summation.
Tuesday, 30 September 2008
Day 106 - Finishing Touches
The skirting has been tacked on the wall temporarily in the new lounge to make the place feel finished even though they will have to return to lay the wood flooring.
The cupboard doors in the kitchen have been tweaked to make them all open and close properly without rubbing against each other.
Not much left, a little coving and the odd strip of wood round the stairs/doorway and we are all done.
Wednesday, 24 September 2008
Day 105 - Electrics Complete
Paul arrived early and cleared the back patio and front of any spare bricks and tiles that I no longer need. The RSJ has gone as well as the plastic guttering that was left over. The place is looking decidedly better. He has also said he will order me some more pea gravel to replace the drive covering that ended up in the footings.
Roger was here again working on the boiler, it looks as though it is all piped in now and the minor change required to reroute the study radiator has also been done. We are STILL awaiting the oil tank.
Tuesday, 23 September 2008
Day 104 - Boiler
Its a big brute and looks man enough to heat the place, though with Luce spinning the dial to 'lava' temperature at any given chance we will see how it lasts. The oil tank should be with us this week so fingers crossed we may get done this week.
Monday, 22 September 2008
Day 103 - Gallery Landing
Friday, 19 September 2008
Day 102 - Small Bits
- The Juliet balcony has been fitted.
- Missing window board fitted in the study
- Upstairs french windows sealed on the outside
- Missing guttering fitted to porch
- Broken guttering fitting replaced
- Hole drilled for utility extractor fan ready for Nigel
- Cleared out all their tools in the lounge
- Screeding some parts of the kitchen to get a better level on the floor
- Screw in faceplates that were left off while plastering
This weekend will be one of painting and tidying up, the boiler is in the garage and I have ordered the oil tank for arrival this week. Phil says he still has a good few days work to get the boiler rigged up and I will have to transfer all the oil to the new tank when its in position. Richard is off all next week as he wants to get on with his house as a moving date is imminent and he is at the plastering stage.
Thursday, 18 September 2008
Day 101 - New Steps
Generally today has been a 'bits 'n' bobs' day other than the steps with little annoying things being completed. Tomorrow Richard wants to clear up some of the other little problems on what he calls his snaglist.
Wednesday, 17 September 2008
Day 100 - Downstairs Doors and Lights
Finally Nigel put up the 4 outside lights around the house so he is all but complete except for minor pieces and the boiler wiring.
Phil has managed to get the the third bedroom to the radiator to give it a second feed after we emptied it the night before. He has also changed the waste on the sink in the bathroom which in the words of my father-in-law developed 'a weep'.
Nigel has also wired up the dishwasher and the waste has been done by Phil so the kitchen is looking pretty good despite not having a floor.
We still have the galleried landing to complete on the list of 'Big things to do' and of course the boiler needs fitting but the end is nigh and everyone has done a good job moving forward today.
Monday, 15 September 2008
Day 99 - Rads
A new radiator has been put in the study replacing the old one with the under-window style, finally a radiator has been put in the hallway as with the extended length of the room having knocked through the porch the nearest radiator is now in the kitchen.
Paul came and filled the old waste from the toilet and the hole that had been made for the bath waste in the previous bathroom, I have been left a note to bond the floor in the kitchen ready for Richard and Ashley to put a final self levelling compound on top prior to your truly tiling the floor.
Friday, 12 September 2008
Day 98 - Utility Room
The Belfast sink in the kitchen was fitted with Richard routing the required holes and grooves as well as on the underside to prevent leaking into the cupboards below. The utility cupboards and sink were also fitted including the waste. The kitchen is fully operational now except for the electrics for the dishwasher and the lighting that came with the units.
James spent most of the day talking about surfboards having become a proud owner of a new board!
Whilst the builders were off-site (we were on holiday and wanted some peace!) we have managed to draft in Luce's folks for some painting, the hallway had had a coat of white emulsion ready for some flavour of off-white Luce will choose. The ceiling in the hall is done thanks to Dave and the master bedroom just needs a second coat and some edging doing to finish it as well.
I have tiled the majority of the bathroom so hopefully Phil can plumb in the shower and put on the shower door. The house is starting to feel more like a home. Back to work next week so things will no doubt slow down again but its looking good.
Monday, 8 September 2008
Day 97 - Cloakroom
I laid tiles and grouted the downstairs cloakroom ready for Phil to refit the toilet and painted the final five downstairs doors ready for fitting. Richard and James continued on the kitchen fitting the trim to the tops and bottoms of the units. We are still without some units and the Belfast sink which are all due on Thursday of this week. Here is how it looks...
With most of the units fitted I cleared the front building yard with James and managed to pack everything into the skip ready for removal, thats the last one so everything had to go, this required some manual assistance....
In the afternoon Phil turned up to fit the toilet back in after tiling. We finally have an action shot of Phil Marsden doing his thing.
Friday, 5 September 2008
Day 96 - Kitchen Fitting...again
Thursday, 4 September 2008
Day 95 - More Kitchen
To be fair he must be over halway, all the the base units are fitted (except a replacement we are due), the worktops in the main kitchen area are on and fitted (and even oiled!) and we have fronts on most of the cupboards.
Tomorrow he is going to get to Magnet to pick up the missed pieces and various odds and ends we have changed as we have gone on. Right now its looking pretty good though...
Once we have the finishing touches on and a few more panels it will be a nice homely kitchen.
Nigel has put in the isolator switches so we dont have to have the fans for the bathrooms going every time we turn on the light switch. We also have working lights now in the new lounge and a switch downstairs to operate the landing lights which was a pain to have to run up and down to turn on/off.
Phil has carried on with the secondary feed to the radiators, the dining room is complete now as well the upstairs second bedroom.
With one day left this week before we have a weeks holiday we are hoping the kitchen will be all but complete tomorrow (If Magnet have a Belfast sink in stock) and maybe the electrics will be complete....we have a control unit left to fit (undecided at present how the TV points will be wired).
Wednesday, 3 September 2008
Day 94 - Pipework & Lights
Phil has started doing the additional work we asked of him, turning all the existing radiators into a two-feed system so that the radiators in the house heat together rather than one after the other. So far he has done all the pipework for the front lounge, study and hallway. The final pipework has also been completed in the cloakroom which we hope to get the tiling on the floor for this weekend.
Tuesday, 2 September 2008
Day 93 - Kitchen FItting
As does the garage and much of the new lounge. We do have the base units in so we get a rough idea of how it will look.
Phil has fitted the downstairs sink and put the pipework in behind the base units for the sink. Nigel has got more faceplates on, we also have two spotlights in the dining area in the kitchen and some fused units upstairs for the towel rails in the bathrooms. We also have extractors fitted in both bathrooms.
The kitchen worktops didnt arrive today as expected but I had a nice call from a lady at Kitchen Surplus who said that the problem was with the couriers and they would have them with me in the morning. Richard left me his usual 'Wot no worktops?' message on a piece of card on the cooker, a true man of the 80's era.
Monday, 1 September 2008
Day 92 - Coving Complete
In every room...
Apart from the study we are all done with plastering and coving, this room will have to be revisited in the future.
Nigel has managed to complete more of the electricity points, ethernet ports, TV points and a shaver point. The way he is moving I should think another day and all the faceplates will be on.
We have a mysterious water patch on the landing we are unsure of. Richard took the floorboards up last week as we thought it was a leak from a pipe having added the unvented system. There are no pipes under that area though which led us to point at our cats, a couple of sniffs of the floor later and they were free from guilt as well. It keeps coming back though so if anyone has an idea then post a comment as we are at a loss.
We have had a delivery of our cooker hood ordered from AKD Appliances on eBay. We were expecting wooden kitchen worktops today but its a no show......maybe tomorrow when we are also expecting the remaining downstairs doors and our Magnet kitchen.
Sunday, 31 August 2008
Weekend Work :(
So finally after clearing the kitchen ready for the week ahead I took this shot, from the picture it looks like we are a eauropean peasant family.......
Yes Luce is posing....
Friday, 29 August 2008
Day 91 - We're Cooking!
The kitchen worktops are due to arrive on Monday and on Tuesday we expect the rest of the Magnet kitchen. Richard is on his own next week but Nigel and Richard are starting to make this hosue feel more homely.
Thursday, 28 August 2008
Day 90 - More Elastictrickery
We have skirting now in the hallway and architrave to match, things are starting to look normal, something is amiss!
Wednesday, 27 August 2008
Day 89 - Doors On
Looks like TV Tony has gone for good, he hasn't responded to Richards calls or e-mails and so we have now got a new electrician coming tomorrow, we have been left a message by Richard saying 'Cooker and lights in by Saturday'. Sounds promising to me.
Tuesday, 26 August 2008
Day 88 - Steps
Richard and James got all the steps in for the upstairs and downstairs. The height of the steps on the downstairs may be a little high but Richard assures us all will be OK when the wood/tiles will be put down.
Richard also managed to sort out some of the kitchen layout with Karl at Magnet Trade, looks like its going to be Padstow design (requires acrobat reader installed). We will be sourcing the worktops ourselves as they only do a 27mm thickness and we would like the thicker 40mm worktops so I am off ebaying tomorrow.
We also have the first of our downstairs oak doors as well which I spent the evening sealing ready to be put up tomorrow. The spindles have also arrived along with the handrail. Hopefully tomorrow we will have a complete upstairs.
News on TV Tony.....well he still hasn't returned and is no longer answering calls so looks like we might end up with a new electrician. The ball is now in Richards court who has to make the final decision. Over the weekend the cooker arrived and we are dying to be able to cook real food again rather than defrosting something and nuking it in the microwave. I think the electrician story may run and run.....
Friday, 22 August 2008
Day 87 - Porch complete
Its a bank holiday weekend this week so no people present until Tuesday.
Thursday, 21 August 2008
Day 86 - Porch Roof
Steve carried on working in the porch boarding the walls ready for plastering. He also finished plastering the front lounge.
Wednesday, 20 August 2008
Day 85 - Front Door
Steve plastered the ceiling although I am unsure if the roof is rainproof yet as roofer James hasn't showed to get the tiles on. James has removed some more of the trim from the old porch opening and its starting to feel like one room now.
The sink has been moved into the utility room and the old pipework running down the interior walls have been moved as well. The water supply pipe is the only thing left.
Phil has rigged us up a working sink and washing machine and with James help we have at least somewhere to wash up. Its not ideal so the sooner we get this kitchen ordered the better.
Steve said he will be back tomorrow and depending on what else we want doing based on how the finances are that could be it for a while. James will be back too. Still no Tony.....
Tuesday, 19 August 2008
Day 84 - Porch Boarded
James got the plasterboard in on the porch ceiling and Steve got the fireplace wall plasterboarded in the lounge so all in all its starting to look like a finished house except for a little woodwork and plaster. We are still miles away from getting some electricity in the new rooms though and using a torch to go to the loo is wearing a little thin......where are you Tony?
Tomorrow is going to be woodwork in the new lounge according to James and Steve might be able to finish plastering the study to make that room ready for Phil.
Monday, 18 August 2008
Day 83 - Plastering Hall
Plastic fascias have been put on the porch but doesn't match the existing peak on the sitting room so thats going to require a few words with James tomorrow. Paul has completed the brickwork ready for roofer James on tuesday. TV Tony has made a shock appearance and done a couple of bits here and there but still hasn't completed the first fit.
James is in charge tomorrow so its any guess what happens :)
Friday, 15 August 2008
Day 82 - Goodbye Kitchen
Steve continued his endless plastering this time the cloakroom and parts of the kitchen were done. Richard was here with Paul finalising construction on the porch roof and getting it ready for roofer James on Tuesday of next week
James will be here on Monday to put the fascia on ready and Paul will be on site too. Richard is away next week as he has a holiday taking his Mum on a cruise....isn't he a nice boy to him Mum.
At the end of the weekend here is the state of play. Upstairs is pretty much complete except for facia plates on all the electrics and lighting fittings. Some more minor woodwork to do on the stairs and in the second bedroom. Downstairs the plastering still needs work on two rooms, the kitchen needs a minor skimming on a couple of walls. Again the electrics need work as do the plumbing for the extra radiators we have discussed with Phil. Making a guess I would say we have 2-3 weeks left. We are still awaiting kitchen quotes.
Our sad looking kitchen.
Thursday, 14 August 2008
Day 81 - Porch & Plaster
We have been told to stay off it until Saturday when it should have dried out enough to take our weight.........most of us are keeping to the rules.
This is our existing lounge at the front, complete with plastered on carpet and brickwork as well as trailing electric wires. Fun.
But thats nothing compared to the kitchen which is looking rather sad now lit only by a builders halogen lamp.
Wednesday, 13 August 2008
Day 80 - Power Cut
Tuesday, 12 August 2008
Day 79 - New Fireplace
Monday, 11 August 2008
Day 78 - En suite fitting
We had one quote back from B&Q at around the £7k mark fitted for the new kitchen but are still awaiting quotes from Magnet and Howdens before we make a final choice.
Update: Got home and they have completed the plasterboarding of the kitchen ceiling and James has got the skirting done in the new master bedroom.
Phil has the sink, toilet and towel rail in the en suite.
Lucie has three designs from Howdens, Hazel the designer has done a cracking job and the designs are all fresh and quite modern looking whilst keeping the traditional look we want to keep in the house. The next question is how much they will cost!
Friday, 8 August 2008
Day 77 - Upstairs Doors
Tony has finished the lights in the ceiling in the new kitchen. This will allow Richard and James to do the ceiling plasterboarding next week.
Thursday, 7 August 2008
Day 76 - Nobody
Expecting people tomorrow.
Wednesday, 6 August 2008
Day 75 - Utility Walls Done
Hazel came round to talk to us about Howdens kitchens and said she would go away and draw up some plans for room designs, hopefully for early next week.
Tony has been about too doing pieces here and there. We have electric points inside the old lounge now and the white trunking on the outside of the house has been removed. He can't really move on with the kitchen due to waiting for the designs to return so we are a little held up now.
Tuesday, 5 August 2008
Day 74 - Bye Bye Porch
The plasterers have been busy too prepping the utility room walls ready for skimming which will finish that room except for the floor screed.
The hallway looks like this now with our hanging light switch.
Phil has been busy today, not only do we have an upstairs sink now but we also have two radiators.
We have Hazel from Howdens tomorrow evening to talk to us about the kitchen design.
Monday, 4 August 2008
Day 73 - Full House
Tony has been finalising some runs and doing some preperation work for the plasterers who want to carry on with the utility room.
Phil has removed the pipework from the old shower to prepare for the plasterers coming into the kitchen. The radiator in the study has also been removed ready for one more in keeping with the new shape of the window.
Richard & James have removed some final beams from the kitchen ceiling and removed the old kitchen door and brick surrounding it, now making it part of the hall. The plasterboard from the old bathroom ceiling has been removed in preperation for plastering.
Derek has finalised the brickwork around the window in the study and done the final bricks in the new cloakroom.
I am guessing tomorrow the plasters will move into the old bathroom/new kitchen area and make the ceiling and walls good.
Lucie and I spent a good part of the weekend talking to kitchen fitting companies. We spoke to www.kitchensdirect.com and had someone draw up a plan but at 10.5k it was a little steep for our budget considering we already have some extras chalked up on APR's bill and likely on TV Tony and Phils too.....only time will tell.
Friday, 1 August 2008
Day 72 - New Lounge Plastered
Thursday, 31 July 2008
Day 71 - Plasterers Return
The floor looks like 10000 Romans have marched through as its covered in the thick plaster they use for the base material.
Tomorrow they are skimming it to finish that room. TV Tony has returned and done a couple of down runs that were missing and started work on the study putting in extra sockets and the two ethernet runs.
Wednesday, 30 July 2008
Day 70 - Upstairs Plastering Done
Tuesday, 29 July 2008
Day 69 - 'Ballroom' roof plastered
Upstairs the end wall of the stairwell has been completed as well and the faces have all been edged ready for completion.
We have moved upstairs in the hope of passing the mess as they go downstairs in the next couple of days.
Monday, 28 July 2008
Day 68 - No More Shower!
On the upside the order is back in for the shower units that were out of stock at Victoria Plumb during the first order and the en suite is all but complete as far as plastering goes, Richard has been in today and built out the back walls the correct distance to allow for headroom.
Plastering is moving on apace, the landing cupboards are done and initial scraping and skimming has taken place on the stairwell. We have decided now is the time to move back upstairs so we can pass miss out on the horror downstairs whilst upstairs returns to some sort of normality.
Saturday, 26 July 2008
Dat 67 - Bathroom Fitting
He even posed so we could get him in the blog!
Friday, 25 July 2008
Day 66 - Plastering again
Luce chose some that weren't bank shattering despite it being a case of 'choose what you like' so in all this extra job has been quick and easy.
Thursday, 24 July 2008
Day 65 - Plastering Continued...
Its been hot again so Steve left early and I can hardly blame him.
Wednesday, 23 July 2008
Day 64 - Landing Plastering
The main part of the landing is complete, the second bedroom is complete and with a bit of skirting will be habitable again. The master bedroom is all ready for plaster with all the edges beaded and taped as required for the plaster to adhere to.
At this rate I think we should be all plastered within a week, soon find out.
Tuesday, 22 July 2008
Day 63 - Spotting 'n' Sticking
Monday, 21 July 2008
Day 62 - Kitchen Clearance
The ceiling of the existing porch that is being rebuilt has also been removed, Luce is worried about spiders!
Friday, 18 July 2008
Day 61 - Tank Disaster
The tank was last filled just before the summer and as we don't use it at all during the summer the 1000 litres they last put in is now making its way down the path and evaporating away!
With that in mind and some assistance from APR who lent me some containers I am currently watching it slowly drain from the tank, and I mean SLOW, its taking hours.
I will have to have a chat with Titan who make it and see if its still under warranty. If not its going to be about £1000 for a new tank.
On to building and the like, Tony has chased out all the wall for the runs inside the old lounge. Next will be disconnecting the old runs from the outside of the house and then bringing them back inside to clean up the look on the outside and do it how it should have been done from the start.
Thursday, 17 July 2008
Day 60 - Mini Doors
I forgot to mention yesterday that this is the message left for us yesterday by Foxy and Co., it reads 'Bill could you please cut your grass as it is makeing the site look very untidy!!!'.....Luce replied writing something about Richard and Lady Boys as he likes his Thai holidays. I don't think this is the end of the banter so watch this space.