We now have a working front door, a guy from the window company came out and did some tweaks to the door edging and got it straight in the opening. With great success too we now have a working front door.
Steve plastered the ceiling although I am unsure if the roof is rainproof yet as roofer James hasn't showed to get the tiles on. James has removed some more of the trim from the old porch opening and its starting to feel like one room now.
This is what remains of the kitchen. The only unit still standing is the broken dishwasher that would prbably be marked as chemical waste due to whats living round the back of it.
The sink has been moved into the utility room and the old pipework running down the interior walls have been moved as well. The water supply pipe is the only thing left.
Phil has rigged us up a working sink and washing machine and with James help we have at least somewhere to wash up. Its not ideal so the sooner we get this kitchen ordered the better.
Steve said he will be back tomorrow and depending on what else we want doing based on how the finances are that could be it for a while. James will be back too. Still no Tony.....